The Menominee Junior and Senior High School continues to prioritize the cleaning of the building. The cleaning team is working hard and moving along. They are currently focused on the first floor, including the ductwork. As of Tuesday of this week,  the second floor is 100 – percent completed, the second-floor ductwork is 100 – percent completed, the second-floor air quality test is completed and satisfactory, the library is 100 – percent completed pending duct cleaning, approximately 98 – percent of the duct work is complete on the first floor, the VOCED area is completed and is waiting air quality testing, and approximately 20 – percent of the gym and cafeteria are completed. The school is also continuing their efforts to find a safe and suitable alternative place for face-to-face instruction. There are several entities working together to try and make this happen. There are just a few more details to resolve and dates to review before moving forward with making a decision.